Art Contracts Ltd is able to demonstrate a sound understanding of the sensitive nature of working within an environment containing children. By their nature children are very inquisitive, and what could be more appealing to a developing mind than a construction site. The welfare and safe being of any individual is paramount, and should always be treated as such, but with children it always seems to take on another dimension. The idealistic time to carry out school works is during the summer holiday break, but with larger contracts they cannot always be completed within this time frame. As such, Art Contracts Limited is appreciative of the need to schedule deliveries around drop off/pick up times and break times.

« Back to Case Studies

Yellow Brick Nursary, Wokingham

Project Particulars
  • Client: Wokingham Borough Council
  • Form of contract: JCT minor Works Building Contract, 2005 edition
  • Value: £205,000
Project Complexities
  • Traffic and pedestrian access had to be carefully planned to facilitate the safe continued use of the facilities.
  • The works were programmed to allow certain rooms to remain in use and then de-canted to rooms which had been completed.
Scope of Works

New build extension and building alteration works to a pavilion building used as a nursery. The works included:

  • Reduced Level Excavation
  • Drainage installation
  • Foundation construction
  • Substructure Brickwork & Blockwork
  • Suspended Ground Floor Slab
  • Superstructure Brickwork & Blockwork
  • Roof Construction—timber roof trusses
  • Roof Coverings
  • External Doors & Windows
  • Carpentry / Electrics. / Plumbing - 1st Fix
  • Replacement boiler
  • Floor Screed & Plasterwork / Ceiling etc.
  • Carpentry / Electrics. / Plumbing - 2nd Fix
  • Sanitaryware etc.
  • Decorations
  • Final Fix - All Trades
  • Floor Finishes
  • Retaining Walls foundations
  • Retaining Wall Superstructure
  • Fencing
Langtree School, Woodcote

Langtree School, Woodcote

Project Particulars
  • Client: Oxfordshire County Council
  • Architect: Mouchel
  • Form of contract: NEC 3 2005
  • Value: £150,000
  • Duration: 12 weeks
Scope of Works
  • Flat to pitched roof conversion
  • Barrel vaulted roof with standing seam roof system
  • Upgrade of current insulation to meet Building Regulation requirements
  • New vertical cladding with composite panel system
  • Installation of new Bull-nosed Fascia & soffit
  • New rainwater goods
Gunter School, Birmingham

Gunter School, Birmingham

Project Particulars
  • Client: Birmingham City Council
  • Architect: Central Site Accommodation
  • Form of contract: Procured under the Birmingham Construction Partnership Framework
  • Value: £40,000
  • Duration: 3 weeks
Scope of Works
  • New Sure Start Centre procured under the Birmingham Construction Partnership Framework
  • Pitched roof structure designed to suit the new modular constructed classrooms
  • Standing Seam roofing system including vapour control layer and insulation to comply with current Building Regulations
  • Bespoke manufactured flashing system
  • Installation of new fascia & soffit
  • Installation of new rainwater goods